Bayou Boulevard resurfacing update

Wednesday, August 19, 2009

I recently contacted Mr. Jim DeVries with the Florida Department of Transportation for an update on the Bayou Boulevard resurfacing project:

Councilman Johnson,
As we discussed yesterday, the FDOT opened bids on August 13th for the resurfacing of Bayou Blvd. from 12th Ave. to Firestone Blvd. The apparent low bidder was APAC Southeast Inc. The department's estimated construction time for this project is 80 days. Construction should begin in late fall.